Burgstallgrabenhütte I 1982 – 25.12.2002
Burgstallgrabenhütte II 2003
4 months rebuilding with furniture
25.Dec.2002 the lodge burned down.
The wave of encouragement gave me the strength to organize our fastest construction site during the crisis.
Herbert Ablinger
28.12.2002 – 02.03 |
designing the new lodge
|
2. – 4.5.2003 |
in situ preparation
|
5.5.2003 |
start of construction
|
28.30.5.2003 |
clear up the place
|
4.7.2003 |
skeleton and roof
|
26.7.2003 |
hermetically sealed
|
15.8.2003 |
interior, natural stones from 2400 m: Many years I saw these stones on the peak, now we brought 5 tons down for the new stoves.
|
Task |
Total
|
Net floor area |
~ 100 m²
|
Net production costs |
~ 220 000 €
|
Client |
Herbert Ablinger
|
Construction period |
June 2003 – Sept. 2003
|